Year Completed 2019
Client Our Coastal Village
Services Roofing, Waterproofing, Exterior Walls
Category Multi-Family, Private
Project Team

View Team

Services Provided

Project Details

Project Details

Project Details

This project was executed in two phases.  The first phase involved reviewing review of the Architect-produced design documents and providing “red-line” mark-ups and comments on the Drawings and Specifications for the architect to incorporate into the permit submission set.  PRC reviewed the building envelope components of the CD’s for compliance with Building Code requirements, manufacturer detailing, and best practice during installation.  The second phase of PRC’s scope involved periodic site visits during construction to observe installation and provide Quality Assurance of the installed building envelope components.  PRC provided mock-up summary reports and follow-up Field Reports following each site visit.